Transmission / Projects / South Scotland

Elmya Dunbar BESS

ELMYA ENERGY UK 1 LIMITED at Thorntonloch 400kV Substation

Connection date
31 Oct 2031
Gate
Gate 1
Status
Scoping
Technology
Storage
Total capacity
400 MW
Connected now
0 MW
Still to connect
400 MW
Transmission owner
SP Energy Networks (SPT)
Agreement type
Direct Connection
Region
South Scotland
Project number
PRO-002290
Tracked since
10 Oct 2026

Change history

Every change to this project across 14 registers from 14 Aug 2026 to 10 Oct 2026.

  • 10 Oct 2026 register
    Added to the register

Also at Thorntonloch 400kV Substation

Substation view

1 other project, 640 MW still to connect at this substation in total.

Status definitions (NESO)

Scoping: NESO is not aware that a planning application has been made.

Awaiting Consents: NESO is aware, or the customer has told it, that a planning application has been made.

Consents Approved: NESO is aware, or the customer has told it, that the planning application has been approved.

These statuses are NESO’s, not QueueWatch’s, and NESO describes them as “as far as we are aware”, so a project may be further along than its status shows.

Source: NESO