Drongan Battery Storage
- Connection date
- 31 Oct 2027
- Gate
- Gate 1
- Status
- Scoping
- Technology
- Storage
- Total capacity
- 100 MW
- Connected now
- 0 MW
- Still to connect
- 100 MW
- Transmission owner
- SP Energy Networks (SPT)
- Agreement type
- Direct Connection
- Region
- South Scotland
- Project number
- PRO-002287
- In the register since
- March 2023
What would CMP470’s commitment fee do to a battery like this? See the use case: Will CMP470’s commitment fee clear the battery queue?
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 20 Mar 2026 registerMarked as Gate 1
- 21 Nov 2025 registerConnection date moved from 20 Oct 2026 to 31 Oct 2027 (+12 months)
- 29 Apr 2025 registerTechnology changed from Demand, Storage to Storage
- 29 Oct 2024 registerConnection point changed from Coylton 275/132/33kV to Coylton 275/132kV
- 27 Sep 2024 registerConnection point changed from Coylton 132/33kV Substation to Coylton 275/132/33kV
- 31 Mar 2023 registerAdded to the register
Also at Coylton 275/132kV
Substation viewNo other projects in the register at this connection point.