Tomchrasky Wind Farm
- Connection date
- 31 Mar 2032 +29 months since 9 Dec
- Gate
- Gate 2
- Status
- Consents Approved
- Technology
- Onshore wind
- Total capacity
- 63 MW
- Connected now
- 0 MW
- Still to connect
- 63 MW
- Transmission owner
- SSEN Transmission (SHET)
- Agreement type
- Direct Connection
- Region
- North Scotland
- Project number
- PRO-002270
- In the register since
- December 2022
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 5 Nov 2026 registerConnection point changed from Tomchrasky Wind Farm 132kV Substation to Tomchrasky Wind Farm 132/33kV Substation
- 5 Nov 2026 registerCapacity changed from 74.4 MW to 63 MW
- 5 Nov 2026 registerConnection date moved from 31 Oct 2029 to 31 Mar 2032 (+29 months)
- 5 Nov 2026 registerStatus changed from Scoping to Consents Approved
- 5 Nov 2026 registerGiven a Gate 2 connection offer
- 23 Dec 2022 registerAdded to the register
Also at Tomchrasky Wind Farm 132/33kV Substation
Substation viewNo other projects in the register at this connection point.