The register still shows a connection date of 12 Jan 2023, which has passed, and the project is not built.
- Connection date
- 12 Jan 2023
- Gate
- Not stated
- Status
- Scoping
- Technology
- Storage
- Total capacity
- 99.8 MW
- Connected now
- 0 MW
- Still to connect
- 99.8 MW
- Transmission owner
- National Grid Electricity Transmission (NGET)
- Agreement type
- Embedded
- Region
- England and Wales
- Project number
- PRO-002261
- Tracked since
- 14 Aug 2026
Change history
Every change to this project across 9 registers from 14 Aug 2026 to 21 Sep 2026.
No changes since 14 Aug 2026. Follow this project to see the next one on your watchlist.
1 other project, 250 MW still to connect at this substation in total.