Saltend North BESS & PV
- Connection date
- 30 Oct 2035
- Gate
- Gate 1
- Status
- Scoping
- Technology
- Storage
- Total capacity
- 200 MW
- Connected now
- 0 MW
- Still to connect
- 200 MW
- Transmission owner
- National Grid Electricity Transmission (NGET)
- Agreement type
- Direct Connection
- Region
- England and Wales
- Project number
- PRO-002236
- In the register since
- December 2022
What would CMP470’s commitment fee do to a battery like this? See the use case: Will CMP470’s commitment fee clear the battery queue?
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 14 Jul 2026 registerMarked as Gate 1
- 29 Oct 2024 registerCapacity changed from 100 MW to 200 MW
- 29 Oct 2024 registerConnection date moved from 30 Oct 2037 to 30 Oct 2035 (−24 months)
- 31 May 2024 registerRenamed from Saltend North BESS
- 31 May 2024 registerCustomer changed from ELGIN ENERGY ES CO LIMITED to EEB74 LIMITED
- 27 Feb 2024 registerConnection point changed from Saltend North GSP to Hedon 275kV Substation
- 23 Dec 2022 registerAdded to the register
Also at Hedon 275kV Substation
Substation viewNo other projects in the register at this connection point.