Rugeley Battery Storage
RUGELEY POWER GENERATION LIMITED at Rugeley 400kV Substation
- Connection date
- Left 8 Sep 2026
- Gate
- Not stated
- Status
- Scoping
- Technology
- Storage
- Total capacity
- 400 MW
- Connected now
- 0 MW
- Still to connect
- 400 MW
- Transmission owner
- National Grid Electricity Transmission (NGET)
- Agreement type
- Direct Connection
- Region
- England and Wales
- Project number
- PRO-002215
- In the register since
- August 2023
What would CMP470’s commitment fee do to a battery like this? See the use case: Will CMP470’s commitment fee clear the battery queue?
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 8 Sep 2026 registerLeft the register (400 MW from 30 Oct 2037)
- 24 Dec 2024 registerConnection date moved from 30 Oct 2033 to 30 Oct 2037 (+48 months)
- 29 Aug 2023 registerAdded to the register
Also at Rugeley 400kV Substation
Substation view1 other project, 600 MW still to connect at this substation in total.