Delays and exits in the transmission queue since 2021How often connection dates move, and how many projects leave the queue. Gate 2 in the transmission queueHow much of the queue has a Gate 2 offer, and what it did to connection dates. The battery queue and CMP470’s commitment feeHow far the battery queue sits above the line that would switch CMP470’s commitment fee off. Changes of customer in the transmission queueHow often connection agreements move between companies, and how those projects fared. Do projects connect on time?How late stages have connected against their connection date in the register. Which connection dates slip least?Which connection dates are pushed back least, allowing for how far ahead they are. Grid outages and the connections due by 2030How many of their planned outages the transmission owners carry out, against the connections due by 2030.

More analyses are on the way.

Transmission / Projects / England and Wales

Ocker Hill - Gresham House

Ocker Hill Storage Limited at Ocker Hill 275kV Substation

Connection date
30 Oct 2029 +24 months since 9 Dec
Gate
Gate 2
Status
Consents Approved
Technology
Storage
Total capacity
240 MW
Connected now
0 MW
Still to connect
240 MW
Transmission owner
National Grid Electricity Transmission (NGET)
Agreement type
Direct Connection
Region
England and Wales
Project number
PRO-002213
In the register since
June 2023

What would CMP470’s commitment fee do to a battery like this? See the use case: Will CMP470’s commitment fee clear the battery queue?

Change history

Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.

  • 22 Oct 2026 register
    Connection date moved from 30 Oct 2027 to 30 Oct 2029 (+24 months)
  • 22 Oct 2026 register
    Status changed from Scoping to Consents Approved
  • 22 Oct 2026 register
    Given a Gate 2 connection offer
  • 29 Aug 2025 register
    Stage removed (0 MW from 30 Oct 2032)
  • 29 Jul 2025 register
    Restructured from 1 stage (240 MW from 30 Oct 2027) to 2 stages (240 MW from 30 Oct 2027, 0 MW from 30 Oct 2032)
  • 31 Jan 2025 register
    Renamed from Murphy Distribution Centre Ocker Hill
  • 29 Oct 2024 register
    Customer changed from MUA ELECTRICITY LIMITED to Gresham House Devco Pipeline Limited
  • 27 Sep 2024 register
    Connection date moved from 30 Oct 2032 to 30 Oct 2027 (−60 months)
  • 28 Jul 2023 register
    Substation name updated in the register (from Ocker Hill GSP to Ocker Hill 275kV Substation)
  • 30 Jun 2023 register
    Added to the register

Also at Ocker Hill 275kV Substation

Substation view

1 other project, 240 MW still to connect at this substation in total.

Status definitions (NESO)

Scoping: NESO is not aware that a planning application has been made.

Awaiting Consents: NESO is aware, or the customer has told it, that a planning application has been made.

Consents Approved: NESO is aware, or the customer has told it, that the planning application has been approved.

Terminated: used by NESO only in its register of 30 April 2021, for two projects that left the register the next month.

These statuses are NESO’s, not QueueWatch’s, and NESO describes them as “as far as we are aware”, so a project may be further along than its status shows.

Source: NESO