Ocker Hill - Gresham House
- Connection date
- 30 Oct 2029 +24 months since 9 Dec
- Gate
- Gate 2
- Status
- Consents Approved
- Technology
- Storage
- Total capacity
- 240 MW
- Connected now
- 0 MW
- Still to connect
- 240 MW
- Transmission owner
- National Grid Electricity Transmission (NGET)
- Agreement type
- Direct Connection
- Region
- England and Wales
- Project number
- PRO-002213
- In the register since
- June 2023
What would CMP470’s commitment fee do to a battery like this? See the use case: Will CMP470’s commitment fee clear the battery queue?
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 22 Oct 2026 registerConnection date moved from 30 Oct 2027 to 30 Oct 2029 (+24 months)
- 22 Oct 2026 registerStatus changed from Scoping to Consents Approved
- 22 Oct 2026 registerGiven a Gate 2 connection offer
- 29 Aug 2025 registerStage removed (0 MW from 30 Oct 2032)
- 29 Jul 2025 registerRestructured from 1 stage (240 MW from 30 Oct 2027) to 2 stages (240 MW from 30 Oct 2027, 0 MW from 30 Oct 2032)
- 31 Jan 2025 registerRenamed from Murphy Distribution Centre Ocker Hill
- 29 Oct 2024 registerCustomer changed from MUA ELECTRICITY LIMITED to Gresham House Devco Pipeline Limited
- 27 Sep 2024 registerConnection date moved from 30 Oct 2032 to 30 Oct 2027 (−60 months)
- 28 Jul 2023 registerSubstation name updated in the register (from Ocker Hill GSP to Ocker Hill 275kV Substation)
- 30 Jun 2023 registerAdded to the register
Also at Ocker Hill 275kV Substation
Substation view1 other project, 240 MW still to connect at this substation in total.