Braybrooke Solar and Battery Connection
- Connection date
- 31 Oct 2031
- Gate
- Not stated
- Status
- Scoping
- Planning consent
- Application submitted 16 Jul 2025
North Northamptonshire, reference 25/00712/FUL · Source: REPD - Technology
- Storage + Solar
- Total capacity
- 500 MW
- Connected now
- 0 MW
- Still to connect
- 500 MW
- Transmission owner
- National Grid Electricity Transmission (NGET)
- Agreement type
- Direct Connection
- Region
- England and Wales
- Project number
- PRO-002207
- In the register since
- December 2022
What would CMP470’s commitment fee do to a battery like this? See the use case: Will CMP470’s commitment fee clear the battery queue?
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 26 Nov 2024 registerConnection point changed from Market Harborough 400kV Substation to Braybrooke (Network Rail) GSP
- 27 Aug 2024 registerConnection point changed from Braybrooke (Network Rail) GSP to Market Harborough 400kV Substation
- 23 Dec 2022 registerAdded to the register
Also at Braybrooke (Network Rail) GSP
Substation viewNo other projects in the register at this connection point.