Womblehill BESS Farm
RE Projects Development Limited at Womblehill BESS Farm 132kV
- Connection date
- 31 Dec 2029
- Gate
- Gate 1
- Status
- Scoping
- Planning consent
- Application submitted 27 Jun 2025
Scottish Government (S36), reference ECU00005233 · Source: REPD - Technology
- Storage
- Total capacity
- 200 MW
- Connected now
- 0 MW
- Still to connect
- 200 MW
- Transmission owner
- SSEN Transmission (SHET)
- Agreement type
- Direct Connection
- Region
- North Scotland
- Project number
- PRO-002197
- In the register since
- December 2022
What would CMP470’s commitment fee do to a battery like this? See the use case: Will CMP470’s commitment fee clear the battery queue?
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 24 Apr 2026 registerMarked as Gate 1
- 31 Jan 2025 registerConnection date moved from 31 Oct 2029 to 31 Dec 2029 (+2 months)
- 23 Dec 2022 registerAdded to the register
Also at Womblehill BESS Farm 132kV
Substation viewNo other projects in the register at this connection point.