Stoke Bardolph 400
ENSO GREEN HOLDINGS LIMITED at Stoke Bardolph 400kV Substation
- Connection date
- 31 Oct 2031 +12 months since 9 Dec
- Gate
- Gate 1
- Status
- Scoping
- Technology
- Storage + Solar
- Total capacity
- 400 MW
- Connected now
- 0 MW
- Still to connect
- 400 MW
- Transmission owner
- National Grid Electricity Transmission (NGET)
- Agreement type
- Direct Connection
- Region
- England and Wales
- Project number
- PRO-002191
- In the register since
- December 2022
What would CMP470’s commitment fee do to a battery like this? See the use case: Will CMP470’s commitment fee clear the battery queue?
Stages
| Stage | Connected MW | Adds MW | Cumulative MW | Date | Gate | Status |
|---|---|---|---|---|---|---|
| 1 | 0 | 200 | 200 | 31 Oct 2031 | Gate 1 | Scoping |
| 2 | 0 | 100 | 300 | 31 Oct 2031 | Gate 1 | Scoping |
| 3 | 0 | 100 | 400 | 31 Oct 2034 | Gate 1 | Scoping |
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 16 Oct 2026 registerStage 1: Connection date moved from 31 Oct 2030 to 31 Oct 2031 (+12 months)
- 16 Oct 2026 registerStage 3: Connection date moved from 31 Oct 2032 to 31 Oct 2034 (+24 months)
- 9 Dec 2025 registerStage 1: Marked as Gate 1
- 9 Dec 2025 registerStage 2: Marked as Gate 1
- 9 Dec 2025 registerStage 3: Marked as Gate 1
- 28 Jul 2023 registerConnection point changed from Stoke Bardolph GSP to Stoke Bardolph 400kV Substation
- 23 Dec 2022 registerAdded to the register
Also at Stoke Bardolph 400kV Substation
Substation viewNo other projects in the register at this connection point.