MARCHWOOD ENERGY STORAGE
- Connection date
- 1 Jun 2028
- Gate
- Gate 1
- Status
- Scoping
- Planning consent
- Granted 13 Nov 2025
New Forest, reference 25/10639 · Source: REPD - Technology
- Storage
- Total capacity
- 200 MW
- Connected now
- 0 MW
- Still to connect
- 200 MW
- Transmission owner
- National Grid Electricity Transmission (NGET)
- Agreement type
- Direct Connection
- Region
- England and Wales
- Project number
- PRO-002190
- In the register since
- November 2022
What would CMP470’s commitment fee do to a battery like this? See the use case: Will CMP470’s commitment fee clear the battery queue?
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 5 May 2026 registerMarked as Gate 1
- 29 Jul 2025 registerConnection date moved from 31 Oct 2027 to 1 Jun 2028 (+7 months)
- 31 Jan 2025 registerCustomer changed from Penso Power Limited to BW ESS DEVELOPMENT UK LIMITED
- 27 Aug 2024 registerRestructured from 1 stage (200 MW from 14 Nov 2031) to 1 stage (200 MW from 31 Oct 2027). First connection date −48 months
- 23 Dec 2022 registerSubstation name updated in the register (from Marchwood 400kV to Marchwood 400kV Substation)
- 29 Nov 2022 registerAdded to the register
Also at Marchwood 400kV Substation
Substation view1 other project, 200 MW still to connect at this substation in total.