Breakish Windfarm
- Connection date
- 31 May 2029
- Gate
- Gate 1
- Status
- Scoping
- Technology
- Onshore wind
- Total capacity
- 99.8 MW
- Connected now
- 0 MW
- Still to connect
- 99.8 MW
- Transmission owner
- SSEN Transmission (SHET)
- Agreement type
- Direct Connection
- Region
- North Scotland
- Project number
- PRO-002170
- In the register since
- May 2023
Stages
| Stage | Connected MW | Adds MW | Cumulative MW | Date | Gate | Status |
|---|---|---|---|---|---|---|
| 1 | 0 | 50 | 50 | 31 May 2029 | Gate 1 | Scoping |
| 2 | 0 | 49.8 | 99.8 | 30 Apr 2034 | Gate 1 | Scoping |
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 20 Oct 2026 registerStage 1: Connection date moved from 30 Apr 2034 to 31 May 2029 (−59 months)
- 16 Oct 2026 registerStage 1: Connection date moved from 31 May 2029 to 30 Apr 2034 (+59 months)
- 16 Oct 2026 registerStage 1: Marked as Gate 1
- 16 Oct 2026 registerStage 2: Marked as Gate 1
- 14 Jul 2026 registerConnection point changed from Breakish 132/33kV to Breakish 132kV Substation
- 6 Mar 2026 registerCustomer changed from ARISE AB to Asuk Holdco 2 limited
- 30 May 2023 registerAdded to the register
Also at Breakish 132kV Substation
Substation viewNo other projects in the register at this connection point.