QueueWatchby QueueQuant Price my project Get the plan that holds up best for your site, and where that answer flips.
Delays and exits in the transmission queue since 2021How often connection dates move, and how many projects leave the queue. Gate 2 in the transmission queueHow much of the queue has a Gate 2 offer, and what it did to connection dates. The battery queue and CMP470’s commitment feeHow far the battery queue sits above the line that would switch CMP470’s commitment fee off. Changes of customer in the transmission queueHow often connection agreements move between companies, and how those projects fared. Do projects connect on time?How late stages have connected against their connection date in the register. Which connection dates slip least?Which connection dates are pushed back least, allowing for how far ahead they are. Grid outages and the connections due by 2030How many of their planned outages the transmission owners carry out, against the connections due by 2030.

More analyses are on the way.

Transmission / Projects / South Scotland

Bankside BESS

FALKIRK POWER LTD at Bainsford 132/33kV

Connection date
24 Nov 2025
Gate
Gate 2
Status
Under Construction/Commissioning
Technology
Storage
Total capacity
43 MW
Connected now
0 MW
Still to connect
43 MW
Transmission owner
SP Energy Networks (SPT)
Agreement type
Embedded
Region
South Scotland
Project number
PRO-002151
In the register since
March 2023

What would CMP470’s commitment fee do to a battery like this? See the use case: Will CMP470’s commitment fee clear the battery queue?

Change history

Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.

  • 18 Sep 2026 register
    Status changed from Consents Approved to Under Construction/Commissioning
  • 19 Jun 2026 register
    Substation name updated in the register (from Bainsford GSP to Bainsford 132/33kV)
  • 19 Jun 2026 register
    Given a Gate 2 connection offer
  • 29 Apr 2025 register
    Connection date moved from 31 Oct 2024 to 24 Nov 2025 (+13 months)
  • 28 Mar 2025 register
    Substation name updated in the register (from Bainsford 132/33kV to Bainsford GSP)
  • 27 Sep 2024 register
    Connection point changed from Bainsford 132kV Substation to Bainsford 132/33kV
  • 29 Aug 2023 register
    Status changed from Scoping to Consents Approved
  • 28 Apr 2023 register
    Agreement type changed from Directly Connected to Embedded
  • 31 Mar 2023 register
    Added to the register

Also at Bainsford 132/33kV

Substation view

No other projects in the register at this connection point.

Status definitions (NESO)

Scoping: NESO is not aware that a planning application has been made.

Awaiting Consents: NESO is aware, or the customer has told it, that a planning application has been made.

Consents Approved: NESO is aware, or the customer has told it, that the planning application has been approved.

Terminated: used by NESO only in its register of 30 April 2021, for two projects that left the register the next month.

These statuses are NESO’s, not QueueWatch’s, and NESO describes them as “as far as we are aware”, so a project may be further along than its status shows.

Source: NESO