Bankside BESS
- Connection date
- 24 Nov 2025
- Gate
- Gate 2
- Status
- Under Construction/Commissioning
- Technology
- Storage
- Total capacity
- 43 MW
- Connected now
- 0 MW
- Still to connect
- 43 MW
- Transmission owner
- SP Energy Networks (SPT)
- Agreement type
- Embedded
- Region
- South Scotland
- Project number
- PRO-002151
- In the register since
- March 2023
What would CMP470’s commitment fee do to a battery like this? See the use case: Will CMP470’s commitment fee clear the battery queue?
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 18 Sep 2026 registerStatus changed from Consents Approved to Under Construction/Commissioning
- 19 Jun 2026 registerSubstation name updated in the register (from Bainsford GSP to Bainsford 132/33kV)
- 19 Jun 2026 registerGiven a Gate 2 connection offer
- 29 Apr 2025 registerConnection date moved from 31 Oct 2024 to 24 Nov 2025 (+13 months)
- 28 Mar 2025 registerSubstation name updated in the register (from Bainsford 132/33kV to Bainsford GSP)
- 27 Sep 2024 registerConnection point changed from Bainsford 132kV Substation to Bainsford 132/33kV
- 29 Aug 2023 registerStatus changed from Scoping to Consents Approved
- 28 Apr 2023 registerAgreement type changed from Directly Connected to Embedded
- 31 Mar 2023 registerAdded to the register
Also at Bainsford 132/33kV
Substation viewNo other projects in the register at this connection point.