Barge Way 120MW BESS
- Connection date
- 31 Oct 2033
- Gate
- Not stated
- Status
- Scoping
- Technology
- Storage
- Total capacity
- 99.9 MW
- Connected now
- 0 MW
- Still to connect
- 99.9 MW
- Transmission owner
- National Grid Electricity Transmission (NGET)
- Agreement type
- Embedded
- Region
- England and Wales
- Project number
- PRO-002144
- In the register since
- July 2023
What would CMP470’s commitment fee do to a battery like this? See the use case: Will CMP470’s commitment fee clear the battery queue?
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 27 Jun 2025 registerSubstation name updated in the register (from Kemsley 132kV Substation to Kemsley GSP)
- 27 Jun 2025 registerCapacity changed from 120 MW to 99.9 MW
- 27 Jun 2025 registerConnection date moved from 31 Oct 2031 to 31 Oct 2033 (+24 months)
- 28 Jul 2023 registerAdded to the register
Also at Kemsley GSP
Substation view1 other project, 99.9 MW still to connect at this substation in total.