Sallachy Wind Farm
- Connection date
- 31 Jul 2028 +11 months since 9 Dec
- Gate
- Not stated
- Status
- Awaiting Consents
- Technology
- Onshore wind
- Total capacity
- 49.5 MW
- Connected now
- 0 MW
- Still to connect
- 49.5 MW
- Transmission owner
- SSEN Transmission (SHET)
- Agreement type
- Embedded
- Region
- North Scotland
- Project number
- PRO-002137
- In the register since
- August 2023
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 24 Sep 2026 registerCustomer changed from WKN SALLACHY LIMITED to SALLACHY WIND LIMITED
- 14 Aug 2026 registerConnection date moved from 31 Aug 2027 to 31 Jul 2028 (+11 months)
- 29 Aug 2023 registerAdded to the register
Also at Cassley GSP
Substation viewNo other projects in the register at this connection point.