Fort Augustus Storage
- Connection date
- 31 Oct 2029
- Gate
- Gate 1
- Status
- Scoping
- Technology
- Storage
- Total capacity
- 900 MW
- Connected now
- 0 MW
- Still to connect
- 900 MW
- Transmission owner
- SSEN Transmission (SHET)
- Agreement type
- Direct Connection
- Region
- North Scotland
- Project number
- PRO-002063
- In the register since
- July 2022
What would CMP470’s commitment fee do to a battery like this? See the use case: Will CMP470’s commitment fee clear the battery queue?
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 16 Oct 2026 registerConnection date moved from 1 May 2031 to 31 Oct 2029 (−18 months)
- 10 Oct 2026 registerConnection date moved from 31 Oct 2029 to 1 May 2031 (+18 months)
- 19 Dec 2025 registerMarked as Gate 1
- 27 Jun 2025 registerTechnology changed from Pumped storage to Storage
- 30 May 2025 registerRenamed from Loch nan Eun PSH
- 31 May 2024 registerCustomer changed from LOCH NAN EUN STORAGE LIMITED to GLENDOE STORAGE LIMITED
- 28 Apr 2023 registerCapacity changed from 600 MW to 900 MW
- 31 Jan 2023 registerRenamed from Loch nan Eun PSH (previously Loch Tarff PSH )
- 23 Dec 2022 registerRenamed from Loch nan Eun PSH
- 28 Oct 2022 registerRenamed from Loch nan Eun PSH (previously Loch Tarff PSH )
- 30 Aug 2022 registerCapacity changed from 300 MW to 600 MW
- 29 Jul 2022 registerAdded to the register
Also at Loch Nan Eun 275/18kV
Substation viewNo other projects in the register at this connection point.