- Connection date
- 4 Oct 2031
- Gate
- Not stated
- Status
- Scoping
- Technology
- Demand + Storage + Solar
- Total capacity
- 400 MW
- Connected now
- 0 MW
- Still to connect
- 400 MW
- Transmission owner
- National Grid Electricity Transmission (NGET)
- Agreement type
- Direct Connection
- Region
- England and Wales
- Project number
- PRO-002056
- In the register since
- August 2022
What would CMP470’s commitment fee do to a battery like this? See the use case: Will CMP470’s commitment fee clear the battery queue?
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 13 Oct 2026 registerCustomer changed from SSE Newchurch Solar Limited to LITTLETON PASTURES SOLAR LIMITED
- 29 Aug 2025 registerCustomer changed from SSE UTILITY SOLUTIONS LIMITED to SSE Newchurch Solar Limited
- 29 Jul 2025 registerTechnology changed from Storage, Solar to Demand, Storage, Solar
- 27 Feb 2024 registerConnection point changed from Dungeness 400kV Substation to Newchurch 400kV Substation
- 23 Dec 2022 registerConnection point changed from Newchurch 400kV to Dungeness 400kV Substation
- 28 Oct 2022 registerConnection point changed from Dungeness 400KV to Newchurch 400kV
- 30 Aug 2022 registerAdded to the register
Also at Newchurch 400kV Substation
Substation viewNo other projects in the register at this connection point.