Balvedavist 162 Battery Storage
- Connection date
- 31 Oct 2030
- Gate
- Not stated
- Status
- Awaiting Consents
- Technology
- Storage + Solar
- Total capacity
- 162 MW
- Connected now
- 0 MW
- Still to connect
- 162 MW
- Transmission owner
- SSEN Transmission (SHET)
- Agreement type
- Direct Connection
- Region
- North Scotland
- Project number
- PRO-002024
- In the register since
- December 2022
What would CMP470’s commitment fee do to a battery like this? See the use case: Will CMP470’s commitment fee clear the battery queue?
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 18 Sep 2026 registerStatus changed from Scoping to Awaiting Consents
- 29 Jul 2025 registerCustomer changed from Sun4net Ltd to S4N SPITTAL LTD
- 27 Jun 2025 registerConnection date moved from 31 Jul 2027 to 31 Oct 2030 (+39 months)
- 30 May 2025 registerTechnology changed from Storage to Storage, Solar
- 31 Jan 2025 registerCustomer changed from S4N SPITTAL LTD to Sun4net Ltd
- 31 Jan 2025 registerTechnology changed from Storage, Solar to Storage
- 24 Dec 2024 registerCustomer changed from Sun4net Ltd to S4N SPITTAL LTD
- 24 Dec 2024 registerTechnology changed from Storage to Storage, Solar
- 30 Jul 2024 registerConnection point changed from Mybster 132/33kV Substation to Spittal 132kV Substation
- 23 Dec 2022 registerAdded to the register
Also at Spittal 132kV Substation
Substation view1 other project, 462 MW still to connect at this substation in total.