Alcemi Midmill BESS
- Connection date
- 31 Dec 2029
- Gate
- Not stated
- Status
- Scoping
- Technology
- Storage
- Total capacity
- 300 MW
- Connected now
- 0 MW
- Still to connect
- 300 MW
- Transmission owner
- SSEN Transmission (SHET)
- Agreement type
- Direct Connection
- Region
- North Scotland
- Project number
- PRO-002014
- In the register since
- August 2022
What would CMP470’s commitment fee do to a battery like this? See the use case: Will CMP470’s commitment fee clear the battery queue?
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 31 Oct 2025 registerRenamed from Alcemi Midmill BESF
- 29 Jul 2025 registerConnection date moved from 31 Oct 2029 to 31 Dec 2029 (+2 months)
- 30 Sep 2022 register300 MW no longer connected
- 30 Sep 2022 registerCapacity changed from 0 MW to 300 MW
- 30 Sep 2022 registerConnection date moved from 31 Oct 2033 to 31 Oct 2029 (−48 months)
- 30 Aug 2022 registerAdded to the register
Also at Kintore 275kV
Substation viewNo other projects in the register at this connection point.