Overhill BESS
PULSE CLEAN ENERGY SPV WATT LIMITED at Rothienorman 2 400/33kV GSP
- Connection date
- 31 Oct 2024
- Gate
- Not stated
- Status
- Consents Approved
- Planning consent
- Granted 1 Mar 2023
Aberdeenshire, reference APP/2022/2252 · Source: REPD - Technology
- Storage
- Total capacity
- 49.9 MW
- Connected now
- 0 MW
- Still to connect
- 49.9 MW
- Transmission owner
- SSEN Transmission (SHET)
- Agreement type
- Embedded
- Region
- North Scotland
- Project number
- PRO-001974
- In the register since
- June 2022
What would CMP470’s commitment fee do to a battery like this? See the use case: Will CMP470’s commitment fee clear the battery queue?
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 24 Feb 2026 registerCustomer changed from Templemurry Limited to PULSE CLEAN ENERGY SPV WATT LIMITED
- 12 Dec 2025 registerConnection point changed from Rothienorman 400kV Substation to Rothienorman 2 400/33kV GSP
- 31 Mar 2023 registerStatus changed from Scoping to Consents Approved
- 23 Dec 2022 registerSubstation name updated in the register (from Rothienorman 400kV to Rothienorman 400kV Substation)
- 30 Jun 2022 registerAdded to the register
Also at Rothienorman 2 400/33kV GSP
Substation viewNo other projects in the register at this connection point.