Meetlaw BESS
- Connection date
- 31 Oct 2031
- Gate
- Not stated
- Status
- Consents Approved
- Planning consent
- Granted 19 Sep 2023
Aberdeenshire, reference APP/2022/2676 · Source: REPD - Technology
- Storage
- Total capacity
- 49.9 MW
- Connected now
- 0 MW
- Still to connect
- 49.9 MW
- Transmission owner
- SSEN Transmission (SHET)
- Agreement type
- Embedded
- Region
- North Scotland
- Project number
- PRO-001966
- In the register since
- March 2023
What would CMP470’s commitment fee do to a battery like this? See the use case: Will CMP470’s commitment fee clear the battery queue?
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 27 Jun 2025 registerConnection date moved from 31 Oct 2028 to 31 Oct 2031 (+36 months)
- 26 Nov 2024 registerStatus changed from Scoping to Consents Approved
- 31 Mar 2023 registerAdded to the register
Also at Fiddes GSP
Substation view3 other projects, 79.9 MW still to connect at this substation in total. 30 MW is due to connect here before this project’s connection date of 31 Oct 2031.