Zenobe Stalybridge Project
- Connection date
- 30 Sep 2027
- Gate
- Not stated
- Status
- Scoping
- Technology
- Storage
- Total capacity
- 150 MW
- Connected now
- 0 MW
- Still to connect
- 150 MW
- Transmission owner
- National Grid Electricity Transmission (NGET)
- Agreement type
- Direct Connection
- Region
- England and Wales
- Project number
- PRO-001940
- In the register since
- September 2022
What would CMP470’s commitment fee do to a battery like this? See the use case: Will CMP470’s commitment fee clear the battery queue?
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 7 Aug 2026 registerStage removed (150 MW from 29 Oct 2029)
- 29 Aug 2025 registerRestructured from 1 stage (150 MW from 30 Sep 2026) to 2 stages (150 MW from 30 Sep 2027, 150 MW from 29 Oct 2029). First connection date +12 months
- 28 Jul 2023 registerConnection point changed from Stalybridge (Network Rail) GSP to Stalybridge 275kV Substation
- 23 Dec 2022 registerConnection point changed from Stalybridge to Stalybridge (Network Rail) GSP
- 30 Sep 2022 registerAdded to the register
Also at Stalybridge 275kV Substation
Substation viewNo other projects in the register at this connection point.