Leithenwater Wind Farm
- Connection date
- 2 Apr 2030
- Gate
- Not stated
- Status
- Scoping
- Technology
- Storage + Onshore wind
- Total capacity
- 72.6 MW
- Connected now
- 0 MW
- Still to connect
- 72.6 MW
- Transmission owner
- SP Energy Networks (SPT)
- Agreement type
- Embedded
- Region
- South Scotland
- Project number
- PRO-001914
- In the register since
- January 2025
What would CMP470’s commitment fee do to a battery like this? See the use case: Will CMP470’s commitment fee clear the battery queue?
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 30 May 2025 registerConnection date moved from 31 Oct 2029 to 2 Apr 2030 (+5 months)
- 31 Jan 2025 registerAdded to the register
Also at Galashiels 132/33kV
Substation viewNo other projects in the register at this connection point.