Tormsdale Windfarm
- Connection date
- 30 Jun 2028 +12 months since 9 Dec
- Gate
- Not stated
- Status
- Scoping
- Technology
- Storage + Solar
- Total capacity
- 70 MW
- Connected now
- 0 MW
- Still to connect
- 70 MW
- Transmission owner
- SSEN Transmission (SHET)
- Agreement type
- Direct Connection
- Region
- North Scotland
- Project number
- PRO-001904
- In the register since
- April 2022
What would CMP470’s commitment fee do to a battery like this? See the use case: Will CMP470’s commitment fee clear the battery queue?
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 14 Aug 2026 registerConnection date moved from 30 Jun 2027 to 30 Jun 2028 (+12 months)
- 30 May 2025 registerTechnology changed from Onshore wind to Storage, Solar
- 31 May 2024 registerCustomer changed from ARISE AB to ASUK HOLDCO 1 LIMITED
- 29 Apr 2022 registerAdded to the register
Also at Mybster 3 132/33kV Substation
Substation view2 other projects, 170 MW still to connect at this substation in total.