Sunbury BESS
- Connection date
- 24 Feb 2031
- Gate
- Not stated
- Status
- Scoping
- Planning consent
- Granted on appeal 16 Jan 2026
Spelthorne, reference 24/01112/FUL · Source: REPD - Technology
- Storage
- Total capacity
- 200 MW
- Connected now
- 0 MW
- Still to connect
- 200 MW
- Transmission owner
- National Grid Electricity Transmission (NGET)
- Agreement type
- Embedded
- Region
- England and Wales
- Project number
- PRO-001883
- In the register since
- November 2022
What would CMP470’s commitment fee do to a battery like this? See the use case: Will CMP470’s commitment fee clear the battery queue?
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 29 Sep 2023 registerConnection point changed from Laleham GSP to Laleham GSP (SEPD)
- 28 Apr 2023 registerCustomer changed from ECODEV GROUP LTD to SUNBURY BESS LTD
- 23 Dec 2022 registerConnection point changed from Laleham 132kV to Laleham GSP
- 29 Nov 2022 registerAdded to the register
Also at Laleham GSP (SEPD)
Substation viewNo other projects in the register at this connection point.