Craig Watch Wind Farm
Craig Watch Wind Farm Limited at CRAIG WATCH WIND FARM 132KV SUBSTATION
- Connection date
- 15 May 2031
- Gate
- Gate 1
- Status
- Awaiting Consents
- Technology
- Onshore wind
- Total capacity
- 72.6 MW
- Connected now
- 0 MW
- Still to connect
- 72.6 MW
- Transmission owner
- SSEN Transmission (SHET)
- Agreement type
- Direct Connection
- Region
- North Scotland
- Project number
- PRO-001877
- In the register since
- March 2022
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 22 Oct 2026 registerMarked as Gate 1
- 17 Mar 2026 registerConnection point changed from Craig Watch Substation to CRAIG WATCH WIND FARM 132KV SUBSTATION
- 30 May 2025 registerConnection date moved from 30 Jun 2029 to 15 May 2031 (+23 months)
- 30 May 2025 registerStatus changed from Scoping to Awaiting Consents
- 24 Dec 2024 registerConnection date moved from 30 Jun 2028 to 30 Jun 2029 (+12 months)
- 27 Feb 2024 registerConnection date moved from 30 Jun 2027 to 30 Jun 2028 (+12 months)
- 30 Mar 2022 registerAdded to the register
Also at CRAIG WATCH WIND FARM 132KV SUBSTATION
Substation viewNo other projects in the register at this connection point.