Delays and exits in the transmission queue since 2021How often connection dates move, and how many projects leave the queue. Gate 2 in the transmission queueHow much of the queue has a Gate 2 offer, and what it did to connection dates. The battery queue and CMP470’s commitment feeHow far the battery queue sits above the line that would switch CMP470’s commitment fee off. Changes of customer in the transmission queueHow often connection agreements move between companies, and how those projects fared. Do projects connect on time?How late stages have connected against their connection date in the register. Which connection dates slip least?Which connection dates are pushed back least, allowing for how far ahead they are. Grid outages and the connections due by 2030How many of their planned outages the transmission owners carry out, against the connections due by 2030.

More analyses are on the way.

Transmission / Projects / England and Wales

Bradford West 100MW

OLD ALLEN ROAD BESS LIMITED at Bradford West 275kV Substation

Connection date
31 May 2027
Gate
Not stated
Status
Consents Approved
Technology
Storage
Total capacity
100 MW
Connected now
0 MW
Still to connect
100 MW
Transmission owner
National Grid Electricity Transmission (NGET)
Agreement type
Direct Connection
Region
England and Wales
Project number
PRO-001874
In the register since
May 2022

What would CMP470’s commitment fee do to a battery like this? See the use case: Will CMP470’s commitment fee clear the battery queue?

Change history

Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.

  • 13 Feb 2026 register
    Customer changed from 24 POWER LTD to OLD ALLEN ROAD BESS LIMITED
  • 27 Jun 2025 register
    Connection date moved from 31 May 2026 to 31 May 2027 (+12 months)
  • 27 Jun 2025 register
    Status changed from Scoping to Consents Approved
  • 29 Apr 2025 register
    Status changed from Consents Approved to Scoping
  • 30 Jul 2024 register
    Connection date moved from 31 Aug 2025 to 31 May 2026 (+9 months)
  • 28 Jul 2023 register
    Substation name updated in the register (from Bradford West GSP to Bradford West 275kV Substation)
  • 28 Jul 2023 register
    Status changed from Awaiting Consents to Consents Approved
  • 30 May 2023 register
    Status changed from Scoping to Awaiting Consents
  • 23 Dec 2022 register
    Substation name updated in the register (from Bradford West to Bradford West GSP)
  • 31 May 2022 register
    Added to the register

Status definitions (NESO)

Scoping: NESO is not aware that a planning application has been made.

Awaiting Consents: NESO is aware, or the customer has told it, that a planning application has been made.

Consents Approved: NESO is aware, or the customer has told it, that the planning application has been approved.

Terminated: used by NESO only in its register of 30 April 2021, for two projects that left the register the next month.

These statuses are NESO’s, not QueueWatch’s, and NESO describes them as “as far as we are aware”, so a project may be further along than its status shows.

Source: NESO