Kilmarnock BESS
- Connection date
- 30 Nov 2026 +1 month since 9 Dec
- Gate
- Gate 2
- Status
- Under Construction/Commissioning
- Technology
- Storage
- Total capacity
- 350 MW
- Connected now
- 0 MW
- Still to connect
- 350 MW
- Transmission owner
- SP Energy Networks (SPT)
- Agreement type
- Direct Connection
- Region
- South Scotland
- Project number
- PRO-001836
- In the register since
- March 2022
What would CMP470’s commitment fee do to a battery like this? See the use case: Will CMP470’s commitment fee clear the battery queue?
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 18 Sep 2026 registerStatus changed from Consents Approved to Under Construction/Commissioning
- 23 Jun 2026 registerConnection point changed from Kilmarnock South 400kV Substation to Boydston 400kV substation
- 23 Jun 2026 registerConnection date moved from 31 Oct 2026 to 30 Nov 2026 (+1 month)
- 23 Jun 2026 registerStatus changed from Scoping to Consents Approved
- 23 Jun 2026 registerGiven a Gate 2 connection offer
- 19 Dec 2025 registerConnection point changed from Kilmarnock South 400/275kV to Kilmarnock South 400kV Substation
- 21 Nov 2025 registerConnection date moved from 31 Jul 2025 to 31 Oct 2026 (+15 months)
- 29 Aug 2025 registerCustomer changed from NORIKER POWER LTD to KILMARNOCK FLEXPOWER LTD
- 29 Apr 2025 registerCustomer changed from KILMARNOCK FLEXPOWER LTD to NORIKER POWER LTD
- 26 Nov 2024 registerConnection point changed from Kilmarnock Town 275/33kV Substation to Kilmarnock South 400/275kV
- 29 Sep 2023 registerCustomer changed from Noriker Power Ltd to KILMARNOCK FLEXPOWER LTD
- 30 Mar 2022 registerAdded to the register
Also at Boydston 400kV substation
Substation viewNo other projects in the register at this connection point.