Delays and exits in the transmission queue since 2021How often connection dates move, and how many projects leave the queue. Gate 2 in the transmission queueHow much of the queue has a Gate 2 offer, and what it did to connection dates. The battery queue and CMP470’s commitment feeHow far the battery queue sits above the line that would switch CMP470’s commitment fee off. Changes of customer in the transmission queueHow often connection agreements move between companies, and how those projects fared. Do projects connect on time?How late stages have connected against their connection date in the register. Which connection dates slip least?Which connection dates are pushed back least, allowing for how far ahead they are. Grid outages and the connections due by 2030How many of their planned outages the transmission owners carry out, against the connections due by 2030.

More analyses are on the way.

Transmission / Projects / South Scotland

Knockkippen Energy Park

KNOCKKIPPEN WIND ENERGY LIMITED at Ayr GSP

Connection date
30 Aug 2028
Gate
Not stated
Status
Scoping
Planning consent
Granted 30 Apr 2025
Scottish Government (S36), reference ECU00004523 · Source: REPD
Technology
Demand + Storage + Solar + Onshore wind
Total capacity
60 MW
Connected now
0 MW
Still to connect
60 MW
Transmission owner
SP Energy Networks (SPT)
Agreement type
Embedded
Region
South Scotland
Project number
PRO-001826
In the register since
March 2022

What would CMP470’s commitment fee do to a battery like this? See the use case: Will CMP470’s commitment fee clear the battery queue?

Change history

Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.

  • 29 Aug 2025 register
    Technology changed from Storage, Solar, Onshore wind to Demand, Storage, Solar, Onshore wind
  • 29 Jul 2025 register
    Customer changed from Naturalis Energy Developments Ltd to KNOCKKIPPEN WIND ENERGY LIMITED
  • 27 Jun 2025 register
    Connection point changed from Ayr 275/33kV to Ayr GSP
  • 27 Jun 2025 register
    Connection date moved from 30 Sep 2026 to 30 Aug 2028 (+23 months)
  • 27 Sep 2024 register
    Substation name updated in the register (from Ayr 275/33 kV Substation to Ayr 275/33kV)
  • 30 Mar 2022 register
    Added to the register

Also at Ayr GSP

Substation view

No other projects in the register at this connection point.

Status definitions (NESO)

Scoping: NESO is not aware that a planning application has been made.

Awaiting Consents: NESO is aware, or the customer has told it, that a planning application has been made.

Consents Approved: NESO is aware, or the customer has told it, that the planning application has been approved.

Terminated: used by NESO only in its register of 30 April 2021, for two projects that left the register the next month.

These statuses are NESO’s, not QueueWatch’s, and NESO describes them as “as far as we are aware”, so a project may be further along than its status shows.

Source: NESO

Planning consent

The planning decision or stage for this project, from DESNZ’s Renewable Energy Planning Database (REPD), July 2026 edition, with the planning authority and its reference. QueueWatch matched the project to that record. NESO’s status can lag behind planning decisions, so the two may differ.