Delays and exits in the transmission queue since 2021How often connection dates move, and how many projects leave the queue. Gate 2 in the transmission queueHow much of the queue has a Gate 2 offer, and what it did to connection dates. The battery queue and CMP470’s commitment feeHow far the battery queue sits above the line that would switch CMP470’s commitment fee off. Changes of customer in the transmission queueHow often connection agreements move between companies, and how those projects fared. Do projects connect on time?How late stages have connected against their connection date in the register. Which connection dates slip least?Which connection dates are pushed back least, allowing for how far ahead they are. Grid outages and the connections due by 2030How many of their planned outages the transmission owners carry out, against the connections due by 2030.

More analyses are on the way.

Transmission / Projects / North Scotland

Teindland Wind Farm

TEINDLAND WIND FARM LIMITED at Blackhillock substation

Connection date
28 Sep 2029
Gate
Not stated
Status
Awaiting Consents
Technology
Demand + Onshore wind
Total capacity
112 MW
Connected now
0 MW
Still to connect
112 MW
Transmission owner
SSEN Transmission (SHET)
Agreement type
Direct Connection
Region
North Scotland
Project number
PRO-001821
In the register since
April 2022

Change history

Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.

  • 18 Sep 2026 register
    Status changed from Scoping to Awaiting Consents
  • 26 Mar 2024 register
    Connection point changed from Teindland 132/33KV Wind Farm Substation to Blackhillock substation
  • 26 Mar 2024 register
    Connection date moved from 31 Oct 2027 to 28 Sep 2029 (+23 months)
  • 26 Mar 2024 register
    Technology changed from Onshore wind to Demand, Onshore wind
  • 29 Apr 2022 register
    Added to the register

Also at Blackhillock substation

Substation view

1 other project, 512 MW still to connect at this substation in total.

Status definitions (NESO)

Scoping: NESO is not aware that a planning application has been made.

Awaiting Consents: NESO is aware, or the customer has told it, that a planning application has been made.

Consents Approved: NESO is aware, or the customer has told it, that the planning application has been approved.

Terminated: used by NESO only in its register of 30 April 2021, for two projects that left the register the next month.

These statuses are NESO’s, not QueueWatch’s, and NESO describes them as “as far as we are aware”, so a project may be further along than its status shows.

Source: NESO