Kirkton Wind Farm
- Connection date
- 29 Oct 2029 +12 months since 9 Dec
- Gate
- Gate 1
- Status
- Awaiting Consents
- Planning consent
- Refused 23 Jan 2026
Scottish Government (S36), reference ECU00003244 · Source: REPD - Technology
- Onshore wind
- Total capacity
- 60 MW
- Connected now
- 0 MW
- Still to connect
- 60 MW
- Transmission owner
- SSEN Transmission (SHET)
- Agreement type
- Direct Connection
- Region
- North Scotland
- Project number
- PRO-001811
- In the register since
- April 2022
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 16 Oct 2026 registerConnection date moved from 31 Oct 2029 to 29 Oct 2029 (2 days earlier)
- 10 Oct 2026 registerConnection date moved from 31 Oct 2028 to 31 Oct 2029 (+12 months)
- 28 Sep 2026 registerMarked as Gate 1
- 18 Sep 2026 registerStatus changed from Scoping to Awaiting Consents
- 29 Oct 2024 registerConnection point changed from Kirkton Wind Farm 132kV Substation to Connagill 275kV Substation
- 29 Oct 2024 registerConnection date moved from 31 Oct 2027 to 31 Oct 2028 (+12 months)
- 29 Apr 2022 registerAdded to the register
Also at Connagill 275kV Substation
Substation view1 other project, 190 MW still to connect at this substation in total.