Kincraig Energy Centre
- Connection date
- 30 Apr 2025 +13 months since 9 Dec
- Gate
- Gate 2
- Status
- Under Construction/Commissioning
- Planning consent
- Granted 18 Oct 2022
Aberdeenshire, reference APP/2022/0838 · Source: REPD - Technology
- Storage + Solar
- Total capacity
- 20.6 MW
- Connected now
- 0 MW
- Still to connect
- 20.6 MW
- Transmission owner
- SSEN Transmission (SHET)
- Agreement type
- Embedded
- Region
- North Scotland
- Project number
- PRO-001810
- In the register since
- March 2023
What would CMP470’s commitment fee do to a battery like this? See the use case: Will CMP470’s commitment fee clear the battery queue?
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 28 Aug 2026 registerGiven a Gate 2 connection offer
- 26 Jun 2026 registerConnection date moved from 30 Apr 2026 to 30 Apr 2025 (−12 months)
- 28 Apr 2026 registerConnection date moved from 29 Mar 2024 to 30 Apr 2026 (+25 months)
- 28 Apr 2026 registerStatus changed from Scoping to Under Construction/Commissioning
- 2 Jan 2026 registerSubstation name updated in the register (from Dyce GSP to Dyce 132/33kV GSP)
- 31 Mar 2023 registerAdded to the register
Also at Dyce 132/33kV GSP
Substation view1 other project, 65.6 MW still to connect at this substation in total.