Rochdale BESS
- Connection date
- 30 Oct 2029 +27 months since 9 Dec
- Gate
- Gate 2
- Status
- Consents Approved
- Technology
- Storage
- Total capacity
- 57 MW
- Connected now
- 0 MW
- Still to connect
- 57 MW
- Transmission owner
- National Grid Electricity Transmission (NGET)
- Agreement type
- Direct Connection
- Region
- England and Wales
- Project number
- PRO-001805
- In the register since
- April 2022
What would CMP470’s commitment fee do to a battery like this? See the use case: Will CMP470’s commitment fee clear the battery queue?
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 18 Sep 2026 registerStatus changed from Scoping to Consents Approved
- 24 Jul 2026 registerConnection date moved from 30 Jul 2027 to 30 Oct 2029 (+27 months)
- 24 Jul 2026 registerGiven a Gate 2 connection offer
- 30 May 2025 registerConnection date moved from 30 Jun 2024 to 30 Jul 2027 (+37 months)
- 31 Jan 2023 registerCustomer changed from SHAW-ENERGI LTD to Rochdale (BES) Ltd
- 23 Dec 2022 registerCustomer changed from Rochdale (BES) Ltd to SHAW-ENERGI LTD
- 23 Dec 2022 registerSubstation name updated in the register (from Rochdale 275kV to Rochdale 275kV Substation)
- 29 Nov 2022 registerCustomer changed from SHAW-ENERGI LTD to Rochdale (BES) Ltd
- 31 May 2022 registerSubstation name updated in the register (from Rochdale to Rochdale 275kV)
- 29 Apr 2022 registerAdded to the register
Also at Rochdale 275kV Substation
Substation viewNo other projects in the register at this connection point.