Zenobe Eccles Battery Storage
- Connection date
- 30 Apr 2026
- Gate
- Gate 2
- Status
- Under Construction/Commissioning
- Planning consent
- Granted 11 Aug 2023
Scottish Government (S36), reference ECU00004601 · Source: REPD - Technology
- Storage
- Total capacity
- 400 MW
- Connected now
- 0 MW
- Still to connect
- 400 MW
- Transmission owner
- SP Energy Networks (SPT)
- Agreement type
- Direct Connection
- Region
- South Scotland
- Project number
- PRO-001779
- In the register since
- March 2022
What would CMP470’s commitment fee do to a battery like this? See the use case: Will CMP470’s commitment fee clear the battery queue?
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 18 Sep 2026 registerStatus changed from Scoping to Under Construction/Commissioning
- 2 Jun 2026 registerGiven a Gate 2 connection offer
- 29 Jul 2025 registerConnection point changed from Eccles 132/33kV to Eccles 400kV Substation
- 29 Oct 2024 registerConnection point changed from Eccles 400/132/33kV to Eccles 132/33kV
- 27 Sep 2024 registerConnection point changed from Eccles 400kV Substation to Eccles 400/132/33kV
- 30 Jul 2024 registerCustomer changed from ZENOBE ENERGY LIMITED to Zenobe Eccles Limited
- 31 Jan 2023 registerCapacity changed from 200 MW to 400 MW
- 23 Dec 2022 registerSubstation name updated in the register (from Eccles 400kV to Eccles 400kV Substation)
- 30 Mar 2022 registerAdded to the register
Also at Eccles 400kV Substation
Substation view1 other project, 900 MW still to connect at this substation in total. 500 MW is due to connect here before this project’s connection date of 30 Apr 2026.