Projects / England and Wales
Ninfield Greener Grid Park
Ninfield Grid Solutions Limited at Ninfield 400kV Substation
- Connection date
- 31 Jan 2031
- Gate
- Not stated
- Status
- Awaiting consent
- Technology
- Storage + Reactive compensation
- Total capacity
- 450 MW
- Connected now
- 0 MW
- Still to connect
- 450 MW
- Transmission owner
- National Grid Electricity Transmission (NGET)
- Agreement type
- Direct Connection
- Region
- England and Wales
- Project number
- PRO-001756
- Tracked since
- 14 Aug 2026
Stages
| Stage | Connected MW | Adds MW | Cumulative MW | Date | Gate | Status |
|---|---|---|---|---|---|---|
| 1 | 0 | 0 | 0 | 30 Apr 2027 | Not stated | Awaiting consent |
| 2 | 0 | 49.9 | 49.9 | 31 Jan 2031 | Not stated | Awaiting consent |
| 3 | 0 | 400.1 | 450 | 31 Oct 2037 | Not stated | Scoping |
Change history
Every change to this project across 9 registers from 14 Aug 2026 to 21 Sep 2026.
No changes since 14 Aug 2026. Follow this project to see the next one on your watchlist.
Also queued at Ninfield 400kV Substation
Substation view1 other project, 1.1 GW still to connect at this substation in total.