Dalmarnock Road BESS
- Connection date
- 23 Feb 2024 +4 months since 9 Dec
- Gate
- Gate 2
- Status
- Under Construction/Commissioning
- Technology
- Storage
- Total capacity
- 40 MW
- Connected now
- 0 MW
- Still to connect
- 40 MW
- Transmission owner
- SP Energy Networks (SPT)
- Agreement type
- Embedded
- Region
- South Scotland
- Project number
- PRO-001660
- In the register since
- November 2021
What would CMP470’s commitment fee do to a battery like this? See the use case: Will CMP470’s commitment fee clear the battery queue?
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 18 Sep 2026 registerStatus changed from Scoping to Under Construction/Commissioning
- 30 Jun 2026 registerConnection point changed from Dalmarnock GSP to DALMARNOCK 132/33KV SUBSTATION
- 30 Jun 2026 registerConnection date moved from 30 Oct 2023 to 23 Feb 2024 (+4 months)
- 30 Jun 2026 registerGiven a Gate 2 connection offer
- 23 Dec 2022 registerSubstation name updated in the register (from Dalmarnock to Dalmarnock GSP)
- 23 Dec 2022 registerAgreement type changed from Directly Connected to Embedded
- 30 Nov 2021 registerAdded to the register
Also at DALMARNOCK 132/33KV SUBSTATION
Substation viewNo other projects in the register at this connection point.