Delays and exits in the transmission queue since 2021How often connection dates move, and how many projects leave the queue. Gate 2 in the transmission queueHow much of the queue has a Gate 2 offer, and what it did to connection dates. The battery queue and CMP470’s commitment feeHow far the battery queue sits above the line that would switch CMP470’s commitment fee off. Changes of customer in the transmission queueHow often connection agreements move between companies, and how those projects fared. Do projects connect on time?How late stages have connected against their connection date in the register. Which connection dates slip least?Which connection dates are pushed back least, allowing for how far ahead they are. Grid outages and the connections due by 2030How many of their planned outages the transmission owners carry out, against the connections due by 2030.

More analyses are on the way.

Transmission / Projects / England and Wales
Connection date
31 Oct 2028
Gate
Not stated
Status
Scoping
Technology
Storage
Total capacity
79.9 MW
Connected now
49.9 MW
Still to connect
30 MW
Transmission owner
National Grid Electricity Transmission (NGET)
Agreement type
Embedded
Region
England and Wales
Project number
PRO-001655
In the register since
September 2021

What would CMP470’s commitment fee do to a battery like this? See the use case: Will CMP470’s commitment fee clear the battery queue?

Stages

StageConnected MWAdds MWCumulative MWDateGateStatus
149.9049.9NoneNot statedBuilt
203079.931 Oct 2028Not statedScoping

Change history

Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.

  • 29 Apr 2025 register
    Customer changed from EAST ANGLIA GRID STORAGE ONE LIMITED to CARE POWER (BURWELL 1) LIMITED
  • 29 Apr 2025 register
    Connection point changed from Burwell Main 400kV Substation to Burwell 132kV Substation
  • 28 Oct 2022 register
    Stage 1: 49.9 MW now connected
  • 28 Oct 2022 register
    Stage 1: Status changed from Scoping to Built
  • 30 Mar 2022 register
    Connection point changed from Burwell to Burwell Main 400kV Substation
  • 31 Dec 2021 register
    Agreement type changed from Directly Connected to Embedded
  • 28 Sep 2021 register
    Added to the register

Also at Burwell 132kV Substation

Substation view

No other projects in the register at this connection point.

Status definitions (NESO)

Scoping: NESO is not aware that a planning application has been made.

Awaiting Consents: NESO is aware, or the customer has told it, that a planning application has been made.

Consents Approved: NESO is aware, or the customer has told it, that the planning application has been approved.

Terminated: used by NESO only in its register of 30 April 2021, for two projects that left the register the next month.

These statuses are NESO’s, not QueueWatch’s, and NESO describes them as “as far as we are aware”, so a project may be further along than its status shows.

Source: NESO