Al Boum Photo (Norton)
- Connection date
- 31 Oct 2031
- Gate
- Not stated
- Status
- Consents Approved
- Technology
- Storage
- Total capacity
- 275 MW
- Connected now
- 0 MW
- Still to connect
- 275 MW
- Transmission owner
- National Grid Electricity Transmission (NGET)
- Agreement type
- Direct Connection
- Region
- England and Wales
- Project number
- PRO-001651
- In the register since
- January 2022
What would CMP470’s commitment fee do to a battery like this? See the use case: Will CMP470’s commitment fee clear the battery queue?
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 26 Apr 2024 registerStatus changed from Awaiting Consents to Consents Approved
- 28 Nov 2023 registerStatus changed from Scoping to Awaiting Consents
- 30 Mar 2022 registerSubstation name updated in the register (from Norton to Norton 400kV Substation)
- 28 Jan 2022 registerAdded to the register
Also at Norton 400kV Substation
Substation viewNo other projects in the register at this connection point.