Delays and exits in the transmission queue since 2021How often connection dates move, and how many projects leave the queue. Gate 2 in the transmission queueHow much of the queue has a Gate 2 offer, and what it did to connection dates. The battery queue and CMP470’s commitment feeHow far the battery queue sits above the line that would switch CMP470’s commitment fee off. Changes of customer in the transmission queueHow often connection agreements move between companies, and how those projects fared. Do projects connect on time?How late stages have connected against their connection date in the register. Which connection dates slip least?Which connection dates are pushed back least, allowing for how far ahead they are. Grid outages and the connections due by 2030How many of their planned outages the transmission owners carry out, against the connections due by 2030.

More analyses are on the way.

Transmission / Projects / England and Wales

Gammidge PV & BESS Park

CS UK HOLDINGS III LIMITED at Grendon 132kV Substation

Connection date
15 Oct 2027
Gate
Gate 1
Status
Scoping
Technology
Storage
Total capacity
40.9 MW
Connected now
0 MW
Still to connect
40.9 MW
Transmission owner
National Grid Electricity Transmission (NGET)
Agreement type
Direct Connection
Region
England and Wales
Project number
PRO-001649
In the register since
April 2021

What would CMP470’s commitment fee do to a battery like this? See the use case: Will CMP470’s commitment fee clear the battery queue?

Change history

Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.

  • 8 May 2026 register
    Marked as Gate 1
  • 24 Dec 2024 register
    Connection date moved from 31 Oct 2024 to 15 Oct 2027 (+35 months)
  • 26 Mar 2024 register
    Connection point changed from Grendon 400kV Substation to Grendon 132kV Substation
  • 26 Mar 2024 register
    Technology changed from Storage, Solar to Storage
  • 28 Nov 2023 register
    Connection point changed from Grendon 132kV Substation to Grendon 400kV Substation
  • 28 May 2021 register
    Connection point changed from Grendon to Grendon 132kV Substation
  • 30 Apr 2021 register
    Added to the register

Also at Grendon 132kV Substation

Substation view

No other projects in the register at this connection point.

Status definitions (NESO)

Scoping: NESO is not aware that a planning application has been made.

Awaiting Consents: NESO is aware, or the customer has told it, that a planning application has been made.

Consents Approved: NESO is aware, or the customer has told it, that the planning application has been approved.

Terminated: used by NESO only in its register of 30 April 2021, for two projects that left the register the next month.

These statuses are NESO’s, not QueueWatch’s, and NESO describes them as “as far as we are aware”, so a project may be further along than its status shows.

Source: NESO