Transmission / Projects / North Scotland

Loch Kemp Pumped Storage

LOCH KEMP STORAGE LIMITED at Loch Kemp 275kV substation

Connection date
Left 30 May 2025
Gate
Not stated
Status
Scoping
Technology
Pumped storage
Total capacity
300 MW
Connected now
0 MW
Still to connect
300 MW
Transmission owner
SSEN Transmission (SHET)
Agreement type
Direct Connection
Region
North Scotland
Project number
PRO-001559
In the register since
August 2021

Change history

Every change to this project across 146 registers from 29 Jan 2021 to 20 Oct 2026.

  • 30 May 2025 register
    Left the register (300 MW from 31 Oct 2027)
  • 29 Jul 2022 register
    Customer changed from STATERA ENERGY LIMITED to LOCH KEMP STORAGE LIMITED
  • 31 Aug 2021 register
    Added to the register

Also at Loch Kemp 275kV substation

Substation view

No other projects in the register at this connection point.

Status definitions (NESO)

Scoping: NESO is not aware that a planning application has been made.

Awaiting Consents: NESO is aware, or the customer has told it, that a planning application has been made.

Consents Approved: NESO is aware, or the customer has told it, that the planning application has been approved.

Terminated: used by NESO only in its register of 30 April 2021, for two projects that left the register the next month.

These statuses are NESO’s, not QueueWatch’s, and NESO describes them as “as far as we are aware”, so a project may be further along than its status shows.

Source: NESO