Slickly Wind Farm
Slickly Wind Farm Limited at Slickly Wind Farm 132kV Substation
- Connection date
- 12 Dec 2029
- Gate
- Not stated
- Status
- Consents Approved
- Technology
- Storage + Onshore wind
- Total capacity
- 114 MW
- Connected now
- 0 MW
- Still to connect
- 114 MW
- Transmission owner
- SSEN Transmission (SHET)
- Agreement type
- Direct Connection
- Region
- North Scotland
- Project number
- PRO-001517
- In the register since
- July 2021
What would CMP470’s commitment fee do to a battery like this? See the use case: Will CMP470’s commitment fee clear the battery queue?
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 21 Nov 2025 registerTechnology changed from Onshore wind to Storage, Onshore wind
- 30 May 2025 registerConnection date moved from 31 Oct 2028 to 12 Dec 2029 (+13 months)
- 30 May 2025 registerStatus changed from Scoping to Consents Approved
- 31 May 2024 registerConnection point changed from Slickly 132/33kV Substation to Slickly Wind Farm 132kV Substation
- 31 May 2024 registerTechnology changed from Storage, Onshore wind to Onshore wind
- 27 Feb 2024 registerRestructured from 2 stages (64 MW from 31 Oct 2027, 50 MW from 31 Oct 2028) to 1 stage (114 MW from 31 Oct 2028). First connection date +12 months
- 28 Apr 2023 registerStage 1: Capacity changed from 49.9 MW to 64 MW
- 28 Apr 2023 registerStage 2: Capacity changed from 64.1 MW to 50 MW
- 28 Feb 2023 registerNew stage added (64.1 MW from 31 Oct 2028)
- 29 Jul 2022 registerTechnology changed from Onshore wind to Storage, Onshore wind
- 30 Jul 2021 registerAdded to the register
Also at Slickly Wind Farm 132kV Substation
Substation viewNo other projects in the register at this connection point.