Salamander Offshore Wind Farm
SALAMANDER WIND PROJECT COMPANY LIMITED at Peterhead 132KV Substation
- Connection date
- 31 Mar 2030
- Gate
- Not stated
- Status
- Scoping
- Planning consent
- Granted 28 Oct 2025
Scottish Government (S36), reference ECU00005201 · Source: REPD - Technology
- Storage + Offshore wind
- Total capacity
- 200 MW
- Connected now
- 0 MW
- Still to connect
- 200 MW
- Transmission owner
- SSEN Transmission (SHET)
- Agreement type
- Direct Connection
- Region
- North Scotland
- Project number
- PRO-001512
- In the register since
- January 2022
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 6 Feb 2026 registerConnection point changed from Peterhead GSP to Peterhead 132KV Substation
- 30 Sep 2025 registerStage removed (0 MW from 31 Mar 2033)
- 29 Jul 2025 registerRestructured from 1 stage (200 MW from 31 Oct 2029) to 2 stages (200 MW from 31 Mar 2030, 0 MW from 31 Mar 2033). First connection date +5 months
- 27 Sep 2024 registerCustomer changed from SIMPLY BLUE ENERGY (SCOTLAND) LTD. to SALAMANDER WIND PROJECT COMPANY LIMITED
- 23 Dec 2022 registerSubstation name updated in the register (from Peterhead to Peterhead GSP)
- 28 Jan 2022 registerAdded to the register
Also at Peterhead 132KV Substation
Substation viewNo other projects in the register at this connection point.