Rawhills Battery Energy Storage Facility(Coalburn 2)
ALCEMI STORAGE DEVELOPMENTS 6 LIMITED at Coalburn 400kV GIS Substation
- Connection date
- 31 Aug 2027 +4 months since 9 Dec
- Gate
- Gate 2
- Status
- Consents Approved
- Planning consent
- Granted 24 Jan 2024
Scottish Government (S36), reference ECU00004698 · Source: REPD - Technology
- Storage
- Total capacity
- 500 MW
- Connected now
- 0 MW
- Still to connect
- 500 MW
- Transmission owner
- SP Energy Networks (SPT)
- Agreement type
- Direct Connection
- Region
- South Scotland
- Project number
- PRO-001503
- In the register since
- May 2021
What would CMP470’s commitment fee do to a battery like this? See the use case: Will CMP470’s commitment fee clear the battery queue?
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 18 Sep 2026 registerStatus changed from Scoping to Consents Approved
- 25 Aug 2026 registerRenamed from Rawhills Battery Energy Storage Facility
- 19 Jun 2026 registerConnection date moved from 16 Apr 2027 to 31 Aug 2027 (+4 months)
- 19 Jun 2026 registerGiven a Gate 2 connection offer
- 31 Mar 2023 registerConnection date moved from 30 Jun 2026 to 16 Apr 2027 (+10 months)
- 30 Jun 2022 registerRenamed from Alcemi Coalburn 2 BESF
- 30 Jun 2022 registerCustomer changed from ALCEMI STORAGE DEVELOPMENTS 4 LIMITED to ALCEMI STORAGE DEVELOPMENTS 6 LIMITED
- 28 May 2021 registerAdded to the register
Also at Coalburn 400kV GIS Substation
Substation viewNo other projects in the register at this connection point.