Tealing Solar & Storage
- Connection date
- 31 Oct 2028 +12 months since 9 Dec
- Gate
- Gate 2
- Status
- Awaiting Consents
- Planning consent
- Granted 13 Dec 2023
Scottish Government (S36), reference ECU00003354 · Source: REPD - Technology
- Storage + Solar
- Total capacity
- 80 MW
- Connected now
- 0 MW
- Still to connect
- 80 MW
- Transmission owner
- SSEN Transmission (SHET)
- Agreement type
- Embedded
- Region
- North Scotland
- Project number
- PRO-001501
- In the register since
- September 2021
What would CMP470’s commitment fee do to a battery like this? See the use case: Will CMP470’s commitment fee clear the battery queue?
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 20 Oct 2026 registerConnection date moved from 31 Oct 2027 to 31 Oct 2028 (+12 months)
- 16 Oct 2026 registerGiven a Gate 2 connection offer
- 23 Jan 2026 registerCustomer changed from ECODEV GROUP LTD to SIRIUS ECODEV (TEALING) LTD
- 27 Jun 2025 registerConnection date moved from 31 Oct 2026 to 31 Oct 2027 (+12 months)
- 28 Sep 2021 registerAdded to the register
Also at Tealing IDNO 132/33kV GSP
Substation viewNo other projects in the register at this connection point.