Thainstone Energy Park
- Connection date
- 31 Oct 2029 +75 months since 9 Dec
- Gate
- Gate 2
- Status
- Consents Approved
- Planning consent
- Granted 25 Jun 2021
Aberdeenshire, reference APP/2020/1324 · Source: REPD - Technology
- Waste
- Total capacity
- 40 MW
- Connected now
- 0 MW
- Still to connect
- 40 MW
- Transmission owner
- SSEN Transmission (SHET)
- Agreement type
- Embedded
- Region
- North Scotland
- Project number
- PRO-001493
- In the register since
- April 2021
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 10 Oct 2026 registerConnection date moved from 30 Oct 2029 to 31 Oct 2029 (1 day later)
- 31 Jul 2026 registerRestructured from 1 stage (40 MW from 30 Oct 2029) to 1 stage (40 MW from 30 Oct 2029)
- 14 Jul 2026 registerRestructured from 1 stage (40 MW from 31 Jul 2023) to 1 stage (40 MW from 30 Oct 2029). First connection date +75 months
- 20 Jan 2026 registerConnection point changed from Kintore GSP to Kintore 132/33kV GSP Substation
- 30 Nov 2021 registerSubstation name updated in the register (from Kintore to Kintore GSP)
- 31 Aug 2021 registerStatus changed from Scoping to Consents Approved
- 30 Apr 2021 registerAdded to the register
Also at Kintore GSP
Substation view1 other project, 1.8 GW still to connect at this substation in total.