Ourack Wind Farm
OURACK WIND FARM LLP at Ourack Wind Farm 132/33 kV Substation
- Connection date
- 31 Oct 2030
- Gate
- Not stated
- Status
- Scoping
- Planning consent
- Granted 25 Mar 2025
Scottish Government (S36), reference ECU00001999 · Source: REPD - Technology
- Storage + Onshore wind
- Total capacity
- 105 MW
- Connected now
- 0 MW
- Still to connect
- 105 MW
- Transmission owner
- SSEN Transmission (SHET)
- Agreement type
- Direct Connection
- Region
- North Scotland
- Project number
- PRO-001490
- In the register since
- October 2022
What would CMP470’s commitment fee do to a battery like this? See the use case: Will CMP470’s commitment fee clear the battery queue?
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 30 Jun 2023 registerTechnology changed from Onshore wind to Storage, Onshore wind
- 28 Oct 2022 registerAdded to the register
Also at Ourack Wind Farm 132/33 kV Substation
Substation viewNo other projects in the register at this connection point.