Wishaw Energy Storage Facility
- Connection date
- Connected
- Gate
- Not stated
- Status
- Built
- Planning consent
- Granted 25 Nov 2020
North Lanarkshire, reference 20/00946/FUL · Source: REPD - Technology
- Storage
- Total capacity
- 50 MW
- Connected now
- 50 MW
- Still to connect
- 0 MW
- Transmission owner
- SP Energy Networks (SPT)
- Agreement type
- Direct Connection
- Region
- South Scotland
- Project number
- PRO-001433
- In the register since
- April 2021
What would CMP470’s commitment fee do to a battery like this? See the use case: Will CMP470’s commitment fee clear the battery queue?
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 29 Oct 2024 registerConnection point changed from Wishaw 400/275/132/33kV to Wishaw 400/275kV
- 27 Sep 2024 registerConnection point changed from Wishaw 33 kV Substation to Wishaw 400/275/132/33kV
- 30 Jan 2024 register50 MW now connected
- 30 Jan 2024 registerStatus changed from Consents Approved to Built
- 31 Mar 2023 registerConnection date moved from 17 Feb 2023 to 4 Apr 2023 (+2 months)
- 23 Dec 2022 registerConnection date moved from 17 Feb 2022 to 17 Feb 2023 (+12 months)
- 29 Nov 2022 registerConnection date moved from 31 Oct 2022 to 17 Feb 2022 (−8 months)
- 30 Mar 2022 registerStatus changed from Scoping to Consents Approved
- 30 Nov 2021 registerConnection date moved from 30 Jun 2023 to 31 Oct 2022 (−8 months)
- 31 Aug 2021 registerCustomer changed from SPECTRUMRESERVE3 LTD to ZENOBE WISHAW LIMITED
- 30 Apr 2021 registerAdded to the register
Also at Wishaw 400/275kV
Substation viewNo other projects in the register at this connection point.