Lethans Wind Farm
- Connection date
- 31 Oct 2029 +28 months since 9 Dec
- Gate
- Gate 2
- Status
- Consents Approved
- Technology
- Onshore wind
- Total capacity
- 132 MW
- Connected now
- 0 MW
- Still to connect
- 132 MW
- Transmission owner
- SP Energy Networks (SPT)
- Agreement type
- Direct Connection
- Region
- South Scotland
- Project number
- PRO-001367
- In the register since
- January 2021 or earlier
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 10 Jul 2026 registerConnection date moved from 30 Oct 2029 to 31 Oct 2029 (1 day later)
- 3 Jul 2026 registerConnection date moved from 30 Jun 2027 to 30 Oct 2029 (+28 months)
- 3 Jul 2026 registerGiven a Gate 2 connection offer
- 6 Mar 2026 registerCustomer changed from BANKS RENEWABLES (LETHANS WIND FARM) LIMITED to Lethans Wind Farm Limited
- 9 Jan 2026 registerConnection point changed from Lethans 132kV Substation to Lethans Collector Substation
- 31 Jan 2023 registerConnection date moved from 31 Oct 2026 to 30 Jun 2027 (+8 months)
- 28 Jan 2022 registerConnection date moved from 30 Jun 2025 to 31 Oct 2026 (+16 months)
- 30 Mar 2021 registerConnection date moved from 26 Jul 2024 to 30 Jun 2025 (+11 months)
Also at Lethans Collector Substation
Substation viewNo other projects in the register at this connection point.