Bridgwater 2 (tertiary) - New Conn
- Connection date
- 31 Aug 2029
- Gate
- Gate 1
- Status
- Scoping
- Technology
- Storage + Solar
- Total capacity
- 57 MW
- Connected now
- 0 MW
- Still to connect
- 57 MW
- Transmission owner
- National Grid Electricity Transmission (NGET)
- Agreement type
- Direct Connection
- Region
- England and Wales
- Project number
- PRO-001347
- In the register since
- January 2021 or earlier
What would CMP470’s commitment fee do to a battery like this? See the use case: Will CMP470’s commitment fee clear the battery queue?
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 9 Dec 2025 registerMarked as Gate 1
- 28 Mar 2025 registerCapacity changed from 54 MW to 57 MW
- 28 Mar 2025 registerConnection date moved from 31 Aug 2028 to 31 Aug 2029 (+12 months)
- 27 Sep 2024 registerConnection date moved from 1 Oct 2024 to 31 Aug 2028 (+47 months)
- 27 Sep 2024 registerTechnology changed from Storage to Storage, Solar
- 27 Aug 2024 registerCustomer changed from ENSO GREEN HOLDINGS H LIMITED to BRIDGWATER GREEN LIMITED
- 31 May 2024 registerCustomer changed from ENSO GREEN HOLDINGS LIMITED to ENSO GREEN HOLDINGS H LIMITED
- 28 Jul 2023 registerSubstation name updated in the register (from Bridgwater 400kV Substation to Bridgewater 400kV Substation)
- 23 Dec 2022 registerSubstation name updated in the register (from Bridgwater 400kV to Bridgwater 400kV Substation)
- 26 Feb 2021 registerConnection date moved from 10 Jan 2024 to 1 Oct 2024 (+9 months)
Also at Bridgewater 400kV Substation
Substation viewNo other projects in the register at this connection point.