Transmission / Projects / South Scotland
Artfield Forest Windfarm
- Connection date
- Left 30 May 2025
- Gate
- Not stated
- Status
- Scoping
- Technology
- Onshore wind
- Total capacity
- 67.2 MW
- Connected now
- 0 MW
- Still to connect
- 67.2 MW
- Transmission owner
- SP Energy Networks (SPT)
- Agreement type
- Embedded
- Region
- South Scotland
- Project number
- PRO-001310
- In the register since
- January 2021 or earlier
Change history
Every change to this project across 146 registers from 29 Jan 2021 to 20 Oct 2026.
- 30 May 2025 registerLeft the register (67.2 MW from 1 May 2026)
- 23 Dec 2022 registerSubstation name updated in the register (from Newton Stewart to Newton Stewart GSP)
- 30 Mar 2022 registerConnection date moved from 1 May 2025 to 1 May 2026 (+12 months)
- 26 Feb 2021 registerConnection date moved from 5 Jan 2025 to 1 May 2025 (+4 months)
Also at Newton Stewart GSP
Substation view1 other project, 72.6 MW still to connect at this substation in total.