QueueWatchby QueueQuant Price my project Get the plan that holds up best for your site, and where that answer flips.
Transmission / Projects / South Scotland

Artfield Forest Windfarm

ARTFIELD FOREST WIND FARM LTD at Newton Stewart GSP

Connection date
Left 30 May 2025
Gate
Not stated
Status
Scoping
Technology
Onshore wind
Total capacity
67.2 MW
Connected now
0 MW
Still to connect
67.2 MW
Transmission owner
SP Energy Networks (SPT)
Agreement type
Embedded
Region
South Scotland
Project number
PRO-001310
In the register since
January 2021 or earlier

Change history

Every change to this project across 146 registers from 29 Jan 2021 to 20 Oct 2026.

  • 30 May 2025 register
    Left the register (67.2 MW from 1 May 2026)
  • 23 Dec 2022 register
    Substation name updated in the register (from Newton Stewart to Newton Stewart GSP)
  • 30 Mar 2022 register
    Connection date moved from 1 May 2025 to 1 May 2026 (+12 months)
  • 26 Feb 2021 register
    Connection date moved from 5 Jan 2025 to 1 May 2025 (+4 months)

Also at Newton Stewart GSP

Substation view

1 other project, 72.6 MW still to connect at this substation in total.

Status definitions (NESO)

Scoping: NESO is not aware that a planning application has been made.

Awaiting Consents: NESO is aware, or the customer has told it, that a planning application has been made.

Consents Approved: NESO is aware, or the customer has told it, that the planning application has been approved.

Terminated: used by NESO only in its register of 30 April 2021, for two projects that left the register the next month.

These statuses are NESO’s, not QueueWatch’s, and NESO describes them as “as far as we are aware”, so a project may be further along than its status shows.

Source: NESO